Elegant Properties, DHA Lahore
Building a House in DHA Lahore: Map Approval, Bylaws and Completion Certificate
Building a house in DHA Lahore goes through six stages with DHA's Building Control Branch, in this order: site plan, drawing (map) approval, possession and demarcation, stage inspections, water and sewer connection, and the completion certificate. Drawing approval takes about 20 working days, DHA's Construction Regulations ask for the house to be finished within 1.5 years of approval (its 2025 brochure says 2 years, so plan for 1.5) and the completion certificate within 3 years.
A DHA house can have a basement, a ground floor and a first floor, up to 35 ft from the crown of the road. On a typical 1 Kanal plot that allows about 4,700 sq ft above ground. Elegant Properties builds grey structure and turnkey houses in DHA Lahore and handles these approvals for its clients.
Last checked: 22 November 2026, against DHA Lahore's Building Control procedures and its Construction Regulations (updated copy published April 2026). DHA can revise these at any time; your architect confirms the version in force.
The Six Steps to Build a House in DHA Lahore
- Site plan. The owner (or a holder of DHA Special Power of Attorney) applies on the green form with a CNIC copy and the allotment letter, after clearing all dues. DHA issues it in 7 working days in Phases 1 to 7 and 9, and 11 working days in Phases 8, 11 and 12. Executive service cuts this to 2 or 3 working days.
- Drawing (map) approval. A registered architect submits the architectural, structural, electrical, plumbing and fire safety drawings with stability certificates, a geotechnical report less than a year old, 3D views and a stamp paper undertaking. Normal review takes 20 working days; executive review 5 working days. Approval is valid for 2 years if work has not started.
- Possession and demarcation. With the approved drawing, a dues clearance and the paid possession challan, DHA marks the plot on the ground. This takes 7 working days (2 on executive service) and is valid for 1 month if construction does not start.
- Construction and stage checks. Work must follow the approved drawing. DHA inspects at set stages and can inspect at any time without notice. Any change to the plan needs prior approval through a DHA-enlisted architect.
- Water and sewer connection. After the structure is complete, apply with elevation photos, the site plan, the electricity connection papers, solar installation certificates and a roof slab stability certificate from a DHA-enlisted engineer. This takes 21 working days. Living in the house before the connection is fined.
- Completion certificate. Apply to the Executive Director Building Control with two front elevation photos, two approved architectural prints, the paid challan and connection fee. It takes 21 working days (5 on executive service) if the house matches the approved drawing.
Source: DHA Lahore, Building Control core procedures brochure (2025); DHA Construction Regulations 2014, updated copy.
DHA Lahore Setbacks by Plot Size
Setbacks (DHA calls them clear spaces) are the parts of the plot that must stay open to the sky. They decide how much of the plot you can cover. Underground water tanks, septic tanks, drains and a 2.5 ft basement stair may sit inside them.
| Plot size | Front | Rear | Each side |
|---|---|---|---|
| 2 Kanal (75 x 120 ft) | 20 ft 9 in | 8 ft 4.5 in | 5 ft 4.5 in |
| 2 Kanal (100 x 90 ft) | 15 ft 9 in | 8 ft 4.5 in | 5 ft 4.5 in |
| 1 Kanal | 15 ft 9 in | 5 ft 4.5 in | 5 ft 4.5 in |
| 10 Marla | 10 ft 9 in | 5 ft 4.5 in | Confirm with your architect |
| 8 Marla | 8 ft | 4 ft | 4 ft |
| 7 Marla | 7 ft | 3 ft | 3 ft |
| 5 Marla | 5 ft | 3 ft | 3 ft |
Source: DHA Construction Regulations, clause 22(a). On a corner plot that keeps its frontage on the longer side, the front setback applies on both road sides (clause 22(c)). An irregular plot keeps at least 3 ft 9 in clear on every side.
How Much Can You Build? Covered Area and Height
DHA Lahore allows a ground floor on everything outside the setbacks, a first floor up to 75% of the ground floor (100% on a 5 Marla plot), and one basement up to 100% of the allowed covered area. A second floor is not allowed. The house may rise to 35 ft from the crown of the road, with the stair mumty capped at 175 sq ft on 10 Marla and smaller plots and 300 sq ft on 1 and 2 Kanal plots.
| Plot (typical dimensions) | Ground floor | First floor | Above ground | With full basement |
|---|---|---|---|---|
| 5 Marla (25 x 45 ft) | about 703 sq ft | about 703 sq ft (100%) | about 1,400 sq ft | about 2,100 sq ft |
| 1 Kanal (50 x 90 ft) | about 2,700 sq ft | about 2,030 sq ft (75%) | about 4,730 sq ft | about 7,430 sq ft |
This is our working from the setbacks above, before porch, stair and mumty adjustments. Plot dimensions differ between phases and blocks, so your architect's drawing gives the exact figure. If the owner installs a solar system of 10 kW or more, clause 67 allows up to 200 sq ft of excess covered area on a 1 Kanal house (300 sq ft on 2 Kanal and above): half of it is not fined and half is fined. Anything beyond that has to be removed.
Other rules that shape the design
- Boundary wall: up to 7 ft from the crown of the road. An electric fence up to 2 ft is allowed on a common wall with the neighbour's NOC; concertina wire is not.
- Plinth: at least 1.5 ft above the road crown without a basement and 3.5 ft with one. The ramp must finish within 5 ft of the boundary wall.
- Car porch: at least 12 ft deep. One porch may rest on the boundary wall on plots of 10 Marla or smaller and on 1 Kanal plots; two on 2 Kanal and 1 Kanal corner plots.
- Basement: one storey, ceiling 9 to 10 ft, with sunken areas allowed into the setbacks if 2.5 ft stays clear.
- Septic tank: every house needs one inside the plot, connected to the main sewer, and DHA inspects the septic tank and ramp together.
Time Limits and Penalties
DHA expects a plot to be built on, and it charges owners who leave it empty or build late. These are the limits that cost money when missed.
| Rule | Limit | If you miss it |
|---|---|---|
| Drawing approval validity | 2 years if work has not started | Fresh approval needed |
| Possession and demarcation validity | 1 month if work has not started | Apply again |
| Start construction | 3 years from the area being opened for possession | Non-construction penalty |
| Finish construction | 1.5 years from drawing approval (regulations, clause 17); DHA's 2025 brochure says 2 years | Late completion charges |
| Completion certificate | 3 years from drawing approval | Monthly fine |
| Living in the house | Only after water and sewer connection | Fine |
| Building against the approved drawing | Not allowed | Stop-work order, disconnection, violation charges or demolition at the owner's cost |
| Demolishing a house without permission | Not allowed | Rs 300,000 violation charge |
Non-utilization fee on empty plots
DHA charges a yearly non-utilization fee on plots that are not built on in Phases 1 to 12 (excluding Phase 9 and Phase 11 Sector IV). For investors it is Rs 75,000 a year up to 10 Marla, Rs 150,000 for 1 Kanal and Rs 300,000 for 2 Kanal. Service-benefit plots pay Rs 40,000, Rs 80,000 and Rs 160,000. Phase 9 and Phase 11 Sector IV pay lower rates: Rs 25,000, Rs 50,000 and Rs 100,000 for investors (Rs 15,000, Rs 30,000 and Rs 60,000 service benefit). Open plots also pay a monthly maintenance charge of Rs 1,000 (5 Marla) to Rs 2,500 (2 Kanal).
Sources: DHA Lahore Building Control brochure (2025); DHA Construction Regulations, clauses 13, 17, 19 and 45; DHA Revised Schedule of Charges w.e.f. 1 July 2025.
What Does It Cost to Build in DHA Lahore?
Construction cost depends on the covered area and the finish level. Our current rates for DHA Lahore are Rs 3,400 to Rs 3,600 per sq ft for grey structure with A-grade materials, and Rs 5,500 to Rs 6,500 per sq ft for a standard turnkey house (Rs 6,500 to Rs 8,500 premium, Rs 10,000 and above luxury).
| House | Covered area (above ground) | Grey structure | Turnkey, standard finish |
|---|---|---|---|
| 5 Marla, ground + first | about 1,400 sq ft | Rs 48 lakh to Rs 51 lakh | Rs 77 lakh to Rs 91 lakh |
| 1 Kanal, ground + first | about 4,730 sq ft | Rs 1.61 crore to Rs 1.70 crore | Rs 2.60 crore to Rs 3.07 crore |
DHA's approval and connection charges, the architect's fee and a basement come on top. See our grey structure construction service, turnkey construction service and the detailed 1 Kanal house construction cost breakdown.
Mistakes That Delay Approval or Cost Money Later
- Buying a plot without checking possession. Construction can only start once DHA opens possession for the area. Check the status before you pay; our plot and file verification guide covers this.
- Using an architect who is not registered with DHA. DHA only accepts drawings signed by an architect registered with the Pakistan Council of Architects and Town Planners and with DHA.
- Changing the plan on site. A room added or a setback covered without revised approval shows up at the completion inspection and blocks the certificate.
- Skipping the completion certificate. Without it DHA fines you every month after the 3-year deadline, and buyers often ask to see it; see our NDC guide.
- Forgetting the solar paperwork. The water and sewer connection now asks for the solar installer's licence and stability certificates.
Building in DHA Lahore: Questions Owners Ask
How long does map approval take in DHA Lahore?
About 20 working days for a normal review and 5 working days on DHA's executive service, once the full drawing set is submitted. The site plan comes before it and takes 7 to 11 working days depending on the phase.
DHA Lahore mein naqsha pass karwane ka tareeqa kya hai?
Pehle site plan lein, phir DHA-registered architect se architectural aur structural drawings, stability certificates aur soil report ke saath submit karwayein. Approval ke baad possession aur demarcation hoti hai, phir construction. Approval 2 saal tak valid hai.
How many floors can I build in DHA Lahore?
A basement, a ground floor and a first floor, up to 35 ft from the crown of the road. A second floor is not allowed on a residential house.
How much of a 1 Kanal plot can be covered in DHA Lahore?
On a typical 50 x 90 ft plot, about 2,700 sq ft on the ground floor and about 2,030 sq ft on the first floor after setbacks, plus a basement up to the allowed covered area.
What happens if I do not build on my DHA plot?
DHA charges a yearly non-utilization fee in Phases 1 to 12 (excluding Phase 9 and Phase 11 Sector IV): Rs 75,000 up to 10 Marla, Rs 150,000 for 1 Kanal and Rs 300,000 for 2 Kanal for investors. Phase 9 and Phase 11 Sector IV pay lower rates (Rs 25,000, Rs 50,000 and Rs 100,000).
When do I need the completion certificate?
Within 3 years of drawing approval. After that DHA adds a monthly fine, and buyers often ask to see the certificate.
Build Your DHA House With Elegant Properties
We build houses in DHA Lahore from grey structure to turnkey, and we handle the site plan, drawing approval, demarcation, connections and completion certificate with DHA. If you do not have a plot yet, we can find one: see plots for sale in DHA Lahore and current DHA plot prices. Our office is at 92-D Broadway Commercial, DHA Phase 8, open 7 days.
More guides: DHA transfer cost and tax calculator · Architectural services · Marla and kanal plot sizes · DHA Lahore phase maps
